Land releases for the Gungahlin Town Centre East project have been delayed by two years, prompting criticism from the Canberra Liberals over the hold-up of plans for 2500 homes, businesses and community spaces.
Canberra Liberal MLA Leanne Castley says Chief Minister Andrew Barr has confirmed that land releases for the project, previously expected in 2025-26, are now forecast for 2027-28.
The project, managed by the Suburban Land Agency, is planned to deliver 2500 homes, including affordable and build-to-rent housing, alongside shops, offices and community spaces.
In March, Barr told the Legislative Assembly that the project’s subdivision design application had been finalised for lodgement in mid-2026, with staged land releases planned from 2026-27.
However, Castley says Barr has now confirmed the application will not be lodged until the fourth quarter of 2026-27, with land releases pushed back to 2027-28.
The revised timetable also affects the government’s June 2026 land release program, which included two residential and commercial sites in Gungahlin Town Centre East for release this financial year.
“Today’s revelation of more delays is just another example of Labor’s neglect of the north,” Castley says.
“I don’t have much faith in the Government’s forecasts. After two years of work, the project is now two years behind schedule.”
Castley has questioned whether the government can complete the subdivision application, secure approvals and finish civil works in time for the revised land release schedule.